Geothermal energy is becoming one of the most efficient solutions for heating and cooling homes and buildings in Spain. However, one of the key steps before installing a geothermal heat pump is deciding between a vertical and a horizontal system, as each has different technical, regulatory, and financial requirements.
In this comprehensive guide, we examine the permits and updated costs for 2025, and provide a clear checklist to help you choose the best option for your project.
1. Horizontal geothermal systems: conditions and requirements
A horizontal ground loop involves burying pipes 1.2–2 m deep in a serpentine or spiral pattern, covering a plot area twice the size of the space to be heated and cooled.
- Land required: at least 400–600 m² of open land for an average detached house.
- Soil conditions: the wetter and more clay-rich the soil, the better its thermal conductivity.
- Restrictions: do not plant deep-rooted trees or cover the trench area with concrete.
- 2025 cost: between €8,000–€12,000 for a standard home (Ecoforest).
- Advantage: more affordable to install if sufficient space is available.
- Disadvantage: slightly lower performance, affected by seasonal variations in ground temperature.
2. Vertical geothermal systems: deep drilling
A vertical ground loop uses boreholes 50–150 m deep, with geothermal probes surrounded by bentonite and cement to ensure thermal contact.
- Requirements: at least 10 m² per borehole to allow drilling.
- Performance: more stable (30–70 W/m, depending on the ground’s thermal conductivity).
- 2025 cost: between €15,000–€25,000 for an average detached house (Ecoforest).
- Installation time: 5–7 days of drilling, 3–4 weeks in total for residential projects (Ecoforest).
- Advantage: takes up little space and works on small urban plots.
- Disadvantage: higher initial investment and drilling permits are required.
3. Permits and regulations in Spain (2025)
The procedures depend on the type of system:
- Horizontal: a minor works permit is usually sufficient.
- Vertical: requires a geotechnical report and notification of the drilling to the regional mining/energy authority. In practice, any borehole deeper than 30 m must be officially registered (Law 22/1973), and a minimum distance from foundations and trees (≥1.5–2 m) may be required (Ecoforest).
- Subsidies: IDAE and regional programs offer grants of up to €4,000 (horizontal) and €7,000 (vertical).
4. CAPEX and OPEX costs in 2025
| Item | Horizontal | Vertical |
|---|---|---|
| Average investment | €8,000–€12,000 | €15,000–€25,000 |
| Annual maintenance | ~€150 | ~€300 |
| Typical SCOP | 3.8–4.3 | 4.5–5.0 |
| Payback period with grants | 8–10 years | 10–12 years |
A detached house in Bilbao with an €18,000 vertical system and annual savings of €1,200 → ROI ≈ 12 years (Ecoforest).
5. Decision checklist: vertical or horizontal?
- ✅ Choose a horizontal geothermal system if…
- Your plot is large (>500 m² of open land).
- You prefer a lower upfront cost.
- You do not mind restrictions on how you use the land (such as not planting deep-rooted trees).
- ✅ Choose a vertical geothermal system if…
- You have limited space or the home is in an urban area.
- You want maximum seasonal performance that remains stable year-round.
- You are looking for a longer service life (probes >50 years).
6. Conclusion
The choice between vertical and horizontal geothermal systems in Spain in 2025 comes down to three factors: available space, upfront budget, and the plot’s regulatory requirements. Both options can deliver savings of 60–75% on heating and cooling, but vertical systems offer higher, more stable performance without the land constraints of horizontal systems.
To learn more about the technology, we recommend reading our cornerstone article: Geothermal heat pumps: an efficient and environmentally responsible alternative. And if you would like to see real-world examples, visit our Ecoforest geothermal projects section, where we showcase both vertical and horizontal installations.